Anacostia River Tunnel in Washington D.C.

Name of Project:

Anacostia River Tunnel in Washington D.C.



Country:
USA

Client:
District of Columbia Water and Sewer Authority (DC Water)

Total value:
€253 million

The Anacostia River Tunnel project, part of the Clean Rivers project of DC Water, involves the construction of a hydraulic tunnel which will mainly be developed under the Anacostia River, a tributary of the Potomac River in Washington.

The tunnel will direct the wastewater and rain water separately to prevent polluting the rivers when there is flooding (combined sewer overflows or CSO) during periods of intense rain.

In addition to the construction of a tunnel, 3.8 km long with a diameter of 7 m, the project will also involve the construction of 6 water intake shafts, approximately 30 m deep.

The tunnel runs along the Ana​​costia River for a total length of 3,800 meters, mostly in clay soils and at an average depth of about 30 meters. When crossing the Anacostia River, the TBM excavated in sandy soils under a hydraulic head of up to 3.5 bar. The tunnel has been lined with fibre reinforced precast concrete segments, which constitute a concrete ring designed for a minimum bend radius of 220 metres and with a final inner diameter of 7 metres. The earth pressure balance (EPB) TBM supplied by Herrenknecht has been set for working at pressures of up to 4 bar in mixed soils of clay and sand under pressure. A secondary lining for the tunnels has not been envisaged. When excavating the tunnel with the TBM, the CSO019 site has served as the main site for the supply of materials and for the spoils of excavated material. For this purpose, the two north and south CSO019 shafts were each served by a gantry crane, with a capacity of 50 and 30 tonnes respectively, and connected by a 100 m long service tunnel. Grouting injections improved the ground underneath foundations and underground utilities, in order to protect the existing infrastructure. This procedure has been partly carried out ahead of TBM excavations, and partly following excavations, as compensation grouting. The 6 shafts are constructed with excavation techniques using bentonite drilling mud for the installation of reinforced concrete diaphragms. Once the diaphragms have been completed, a dewatering system is installed. This consists of a series of shafts with small diameters and equipped with pumps capable of reducing the hydraulic pressure of the groundwater, so as to allow excavations in the shaft in well-drained conditions. Once excavation works with the TBM have been completed, the shafts has been lined with concrete by means of 5 circular formworks, the diameter varying according to the shaft being lined. Other concrete structures included: diversion chambers, which connect the existing structure with the new tunnel; odor control units i.e. ventilation and gas control chambers; an overflow structure; and other hydraulic structures inside the shaft. Finally, the shafts and the maintenance chambers are equipped with electromechanical equipment and put into service.

Recognitions: The project received on November 2017 the Sustainability Initiative of the Year award from the International Tunnelling and Underground Space Association (ITA-AITES), the leading international organization promoting the use of tunnels and underground space for sustainable development through knowledge sharing and the application of technology.

MAIN TECHNICAL DATA:
6 shafts which vary in diameter from 9 to 22 m and approximately 30 m deep
1 soft ground tunnel with a minimum internal diameter of 7 metres and approximately 3,800 metres long, entirely lined in prefabricated segments
4 diversion chamber
3 connections between shafts and the main tunnel
5 odour control units
Electromechanical works
Connecting works with the existing infrastructures

 

washington  aerial view
WORKS & PROJECTS - 07/12/2016A TUNNEL TO HELP WASHINGTON, D.C., CLEAN ITS RIVERS

The city is having built a series of tunnels to better manage sewage and storm waters

Last update: 03/06/2019

OTHER PROJECTS: USA