Dualisation of Suleja - Minna Road, Niger State

Name of Project:

Dualisation of Suleja - Minna Road, Niger State



Country:
Nigeria

Client:
Federal Government of the Federal Republic of Nigeria

Total value:
€ 48 million

Start of works:
October 2010

Expected duration:
52 months

The project involves the doubling of the carriageway of the Suleja - Minna road for a length of 40 km. The street axis of the town of Dikko ends in the village of Bonju; the works involve extending the current section of road, going from 7.3 m to 26.1 m.

There are 3 bridges over the river in this section, which vary in length from 30 m to 120 m, and 2 overpasses up to 60 m long.

MAIN TECHNICAL DATA:
Excavations and earth moving: 338,957 m3
Drainage channels: 32,598 m
Crushed aggregate base: 61,970 m3
Surface asphalt: 609,850 m2
Binder : 601,850 m2
Pavement: 601,850 m2
 

 

OTHER PROJECTS: Nigeria

Last update: 09/02/2015