Orastie - Sibiu Motorway, lot 3

Name of Project:

Orastie - Sibiu Motorway, lot 3



Country:
Romania

Client:
Romanian National Company of Motorways and National Roads

Total value:
€137 million

Start of works:
September 2011

Expected duration:
28 months

The Orastie - Sibiu project is part of a wider project known as the “No 4 motorway corridor” which will connect the town of Nadlac, located at the border with Hungary, to the town of Constanta, located on the western shore of the Black Sea.
The contract will involve the construction of 22.1 km of dual carriageway motorway with two lanes, as well as a hard shoulder with an overall width of 26 metres.
Some of the main civil works include the construction of a viaduct, approximately one kilometre long and 80 metres tall.

MAIN TECHNICAL DATA:
Excavations: 3,882,976 m³
Embankments: 218,164 m³
Bridge concrete: 68,835 m³
Bridge formwork: 15,031 m²