Third lane of the A4 between Quarto d’Altino and San Donà di Piave (Ve)

Name of Project:

Third lane of the A4 between Quarto d’Altino and San Donà di Piave (Ve)



Country:
Italy

Client:
Autovie Venete S.p.A.

Total value:
€224 million, share €78 million

Start of works:
September 2011

Expected duration:
46 months

The project involves the extension of the third lane of the A4 Venice-Trieste Motorway in the section between the municipalities of Quarto D’Altino and San Donà di Piave (Ve).
The extension works involve a section approximately 18.5 km long and include the construction of two new viaducts on the Piave River for a length of 1.4 km, the building of 4 bridges, 9 overpasses, 4 motorway underpasses and the resurfacing of the San Donà di Piave motorway interchange.

MAIN TECHNICAL DATA:
Excavations: 1,124,000 m3
Foundations: 256,000 m3
Embankment: 1,327,000  m3
Steel for reinforcements (excluding stakes): 17,546,000 kg
Structural steel: 15,063,000 kg
Concrete (excluding stakes): 84,500 m3
Formwork: 68,600 m2

OTHER PROJECTS: Italy

Last update: 18/09/2013