Köseköy-Gebze section of high speed railway

Name of Project:

Köseköy-Gebze section of high speed railway



Country:
Turkey

Client:
Central Finance and Contracts Unit – CFCU

Total value:
€ 146.8 million

Rehabilitation and reconstruction of Köseköy-Gebze section of the Ankara-Istanbul High Speed Rail. Works include reconstruction of 56 km of double track railway, construction of infrastructure and superstructure of railway and electromechanical works as electrification, signalization and telecommunication of the line. The completion of the project will provide a safe and modern transport system.

MAIN TECHNICAL DATA:
Route & borrow excavation: 1,675,581 m3
Foundation excavation & backfill: 120,476 m3
Embankment: 349,580 m3
Total concrete volume: 39,731 m3
Stone fortification: 107,622 t
Ballst supply and laying: 245,080 m3
Rail removal of old line: 111,400 m
Rail laying on new line: 111,400 m